Notes from ERLP Planning Meeting 4th April 2007

The halo is around 50% of the beam. This number is not confirmed, so we should try to repeat the measurement using a scanning slit.

Make sure that no cryo equipment is left on the floor at the end of cryo commissioning.
Yuri/Philippe on Shift 1